Every batch of shisha briquettes goes through the same six checks, in the order the factory makes them. Each check leaves a record, and the last thing kept is a sample of the batch, the reference for any claim on this hookah charcoal.

Published by
PT Nargile Coconut Charcoal Indonesia
Published
Updated
A hand check at packing takes out chipped or cracked pieces before a box is closed.

In short

What does the factory check, at which step, and what makes it reject a batch?

Six checks run in production order, from the shell charcoal on arrival to a hand check of every piece at packing. Between them come size four times a day, moisture after every oven load, a burn test and a drop test. A batch fails on smell or smoke as the pieces warm up, high ash, cracked or broken pieces or pieces of uneven size or density.

1. The checks in production order

Six checks run in the order of production. The table gives what each one checks and how, as the factory declares it.

The factory's checks in production order, what each one checks and how, as declared by the factory.
CheckWhat is checkedHow
On arrival The shell charcoalmoisture under 12%, at least 82% fixed carbon, at most 14% volatile matter, the ash content and the color of the ash
Size The pressed piecesfour times a day, 20 pieces go under a digital caliper and each reading is logged
Drying Every oven load48 hours or more per batch; moisture measured with a meter on every oven load; 2% at most
Burn test Pieces of the batchthree pieces go on an electric coil; the time each takes to light and how long it burns are logged
Drop test Lit piecesa lit piece is dropped on a hard tiled floor, from 30 cm for hexagonal, dome and finger shapes and from 100 cm for cube and flat shapes; it passes if it stays whole after three drops
Packing Every pieceEach piece is inspected by hand as it is packed

Every limit behind these checks is in one table on the limit behind each check.

2. On arrival

The shell charcoal is checked on arrival for moisture under 12%, at least 82% fixed carbon, at most 14% volatile matter, the ash content and the color of the ash.

These are the raw material's limits: moisture content, fixed carbon, volatile matter and ash content, with the color of the ash looked at as well.

3. During production

Four checks run while the pieces are made: the size, the moisture after drying, and two tests on lit pieces.

  • Size: four times a day, 20 pieces go under a digital caliper and each reading is logged; the size tolerance is ±0.3 mm per side.
  • Moisture: 48 hours or more per batch; moisture measured with a meter on every oven load; 2% at most.
  • The burn test: three pieces go on an electric coil; the time each takes to light and how long it burns are logged.
  • The drop test: a lit piece is dropped on a hard tiled floor, from 30 cm for hexagonal, dome and finger shapes and from 100 cm for cube and flat shapes; it passes if it stays whole after three drops.
A digital caliper reads the edge of a cube to a hundredth of a millimeter.

Three of these checks can be repeated on a sample: see testing a sample the same way.

4. At packing

Each piece is inspected by hand as it is packed. It is the last of the six checks.

How the pieces come to the packing table, from the press to the ovens, is on the production steps.

5. What fails a batch

Definition

batch

A batch is the quantity of briquettes pressed and dried together and checked as one unit.

Four signs fail a batch, and a batch that fails is set aside; it is not ground and pressed again.

  • Smell or smoke as the pieces warm up
  • High ash
  • Cracked or broken pieces
  • Pieces of uneven size or density

High ash is judged against the grade's range, as each order's lab report gives it: see the lab report of each order.

6. Records and the retained sample

The records of the checks are kept by the shipping coordinator, under Yudha Prakoso (Logistics Manager). The buyer receives weekly updates on production, packing, quality checks and stuffing, every Monday; photographs of the empty container before loading and of the load.

The factory keeps about 25 kg of every batch for 5 years, sealed in bags marked with the batch number and date. This retained sample is what a quality claim is checked against.

Labels on sealed sample bags tie each bag to the batch it came from.

Note

A claim is made for quantity within one week and for quality within two weeks, counted from the day the container reaches the buyer's warehouse; the buyer's report is checked against the retained sample; a claim that holds is settled with a credit on the next order; the decision can go to a laboratory or a surveyor, and the cost is shared. How a claim runs is on a claim against the retained sample.

Questions buyers ask

Who keeps the records of the checks?
The records are kept by the shipping coordinator, under Yudha Prakoso (Logistics Manager).
Will I see the checks made on my order?
The factory sends weekly updates on production, packing, quality checks and stuffing, every Monday; photographs of the empty container before loading and of the load.

Test a sample the same way

The sample form asks for the sizes and grades you want to compare and the address to send them to.

Request a sample